Cuba_ As part of the investment plan of the Delegation of Water Resources in Havana and in order to improve the guarantee and stability of the water service, a conductor is replaced in the territory, Radio Reloj reports.
The sub delegate of inversions of Hidraulic Resources in the Cuban capital, Pedro Sánchez, said that this work, which runs from the Santa Catalina avenues to San Anastasio in the municipality of Diez de Octubre, will replace the conductor of Milagros street, with a deplorable technical condition.
He added that the task has a cost of four and a half million pesos, and includes the execution of four kilometers with 900 mm diameter pipes of high density polyethylene.
The construction of the conductor, which has a work schedule of 90 days and will benefit the neighbors of the municipality of Diez de Octubre, is in charge of the Construction Company of Hydraulic Resources of the West.
Â
Â